Legislative budget schedulers set a November review for Taichung MRT Green Line phase-two land acquisitions after city officials warned that delayed expropriation payouts were pushing main tunnel contract bids into 2027, two years behind the original campaign promise.
The Green Line extension aims to link Taichung High Speed Rail station with the Taiwan Boulevard corridor, where office towers and university hospitals generate rush-hour crowds buses struggle to serve. Phase one opened in April with higher-than-expected ridership, raising pressure to fund phase two before the 2026 local election cycle peaks.
Where land talks stalled
City expropriation panels still owe compensation on nine parcels near Fengyuan, where owners challenged assessed values in administrative courts. Taichung Mayor Lu Shiow-yen told lawmakers Thursday that the delays forced designers to shrink a maintenance yard, which in turn limits train stabling capacity at peak hours.
Central government grants cover roughly half the NT$98 billion phase-two price tag, but only if Taichung completes land acquisition milestones by March. Missing those gates would trigger a reprogramming fight in the Yuan just as other cities seek rail matching funds.
Yuan politics
Opposition legislators demanded independent appraisals, alleging some valuations favored connected developers. Ruling caucus members countered that court appeals, not malice, caused the backlog, and proposed a one-time arbitration pool administered by the Public Construction Commission.
The scheduled review will examine whether national land banks can advance payments and recoup costs after cases settle — a tool used on Taipei MRT extensions but never yet for Taichung.
Commuter stakes
Commuter groups from Tunghai University and Feng Chia University said bus crowding returned after schools reopened this fall. Without phase two, they argued, Taichung’s car ownership rate will climb even as the city promotes carbon reduction pledges.
Construction firms bidding on the tunnel package asked the city to clarify geotechnical data from old irrigation channels before tender deadlines in January. Any further land delay makes it likely only one qualified joint venture will bid, raising monopoly concerns watchdog groups flagged in a letter to the Ministry of Transportation and Communications.
Environmental review
Environmental impact assessors still owe a supplemental report on groundwater pumping during tunnel boring near the Daan River. Activists want night-time noise caps enforced on ventilation shaft construction, citing complaints from night-market vendors whose stalls line nearby alleys.
City planners said they will publish a bilingual project timeline at open houses next week, a transparency step demanded after earlier rail projects hid delay notices in technical appendices.